联合国国际货物销售合同公约(英文)
(b) his conduct in preparing to perform or in performing the contract.
(2) If the seller has already dispatched the goods before the grounds described in the preceding paragraph become evident, he may prevent the handing over of the goods to the buyer even though the buyer holds a document which entitles him to obtain them. The present paragraph relates only to the rights in the goods as between the buyer and the seller.
(3) A party suspending performance, whether before or after dispatch of the goods, must immediately give notice of the suspension to the other party and must continue with performance if the other party provides adequate assurance of his performance.
Article 72
(1) If prior to the date for performance of the contract it is clear that one of the parties will commit a fundamental breach of contract, the other party may declare the contract avoided.
(2) If time allows, the party intending to declare the contract avoided must give reasonable notice to the other party in order to permit him to provide adequate assurance of his performance.
(3) The requirements of the preceding paragraph do not apply if the other party has declared that he will not perform his obligations.
Article 73
(1) In the case of a contract for delivery of goods by instalments, if the failure of one party to perform any of his obligations in respect of any instalment constitutes a fundamental breach of contract with respect to that instalment, the other party may declare the contract avoided with respect to that instalment.
(2) If one party's failure to perform any of his obligations in respect of any instalment gives the other party good grounds to conclude that a fundamental breach of contract will occur with respect to future instalments, he may declare the contract avoided for the future, provided that he does so within a reasonable time.
(3) A buyer who declares the contract avoided in respect of any delivery may, at the same time, declare it avoided in respect of deliveries already made or of future deliveries if, by reason of their interdependence, those deliveries could not be used for the purpose contemplated by the parties at the time of the conclusion of the contract.